Abstract:
The Quantities and Workload Model is established by improving the earned value method. The model tends to simplify, standardize, quantify and informationize the complex process and cost data of building nuclear power project, providing the nuclear power AE company more standardized, delicate, personalized information, which can be used in management activities such as multi-project management, and delicate management and project accounting. This paper describes the process of establisheding the model and its characteristics, and makes a deep research on the model’s application.