Engineering Application Problems of Degradable Waste Processing Facilities in Tianwan Nuclear Power Plant and Resolutions of the Problems
-
摘要: 田湾核电站为国内首家引入可降解防护用品及处理设施(简称可降解设施)的核电厂,该套设施首次安装在核电厂核岛辐射控制区内,在工程设计、安装调试等方面遇到了一系列问题,本文就田湾核电站可降解处理设施工程实践中遇到的较为典型的问题及其处理过程进行了梳理,并为后续可降解设施的应用提出了建议。Abstract: Tianwan Nuclear Power Plant is the first nuclear power plant in China to introduce degradable protective articles and its processing facilities. This set of processing facilities was also installed for the first time in the radiation control area of the nuclear island of the nuclear power plant. We have encountered a series of problems in engineering design, installation and commissioning. This paper reviews and analyzes the problems encountered in the engineering practice of the degradable waste processing facilities and the process of solving these problems and also proposes suggestions for the future application of the degradable waste processing facilities facilities.
-