XU Yonghua. Risk Analysis on Safety Injection Test of PWR Nuclear Power Plant[J]. Nuclear Power Engineering, 2012, 33(6): 27-29.
Citation: XU Yonghua. Risk Analysis on Safety Injection Test of PWR Nuclear Power Plant[J]. Nuclear Power Engineering, 2012, 33(6): 27-29.

Risk Analysis on Safety Injection Test of PWR Nuclear Power Plant

  • Received Date: 2011-08-03
  • Rev Recd Date: 2012-05-30
  • Available Online: 2025-03-08
  • During the safety injection(SI) test in the PWR nuclear power plant,full water in pressurizer and high-high level,low-low level in SG may take place.This paper analyzes the risks and response measures in the SI test.Focusing on the full scale problem of pressurizer thermal calibration level gauge in the SI test of nuclear power plant,the test process is analyzed and the problems that should be noted in the SI test are summed up.

     

  • loading
  • 加载中

Catalog

    通讯作者: 陈斌, bchen63@163.com
    • 1. 

      沈阳化工大学材料科学与工程学院 沈阳 110142

    1. 本站搜索
    2. 百度学术搜索
    3. 万方数据库搜索
    4. CNKI搜索

    Article Metrics

    Article views (18) PDF downloads(0) Cited by()
    Proportional views
    Related

    /

    DownLoad:  Full-Size Img  PowerPoint
    Return
    Return