Study on Initial Passivation Process of Primary Loop of PWR Nuclear Power Plants

  • Publish Date: 2020-04-11
  • The development of the passive oxide film on the primary loop during hot functional testing of PWR nuclear power plants is very important in the minimizing corrosion of the materials and corrosion product release. In this paper, based on the theoretical research and engineering practice, it is concluded  that the electrochemical reaction and the chemical reaction exist in the formation of the passive oxide film  during the hot functional testing, and the growth mechanism of the double-layer film is explained. The reasonableness of the analysis of passivation test by electrochemical measurement method is demonstrated. The functional relationship between passivation temperature and passivation film reaction rate is deduced. When the temperature increases, the reaction rate will increase and the passivation time shortens. The theoretical limit of passivation temperature should not be lower than 260℃.

     

  • loading
  • 加载中

Catalog

    通讯作者: 陈斌, bchen63@163.com
    • 1. 

      沈阳化工大学材料科学与工程学院 沈阳 110142

    1. 本站搜索
    2. 百度学术搜索
    3. 万方数据库搜索
    4. CNKI搜索

    Article Metrics

    Article views (260) PDF downloads(3) Cited by()
    Proportional views
    Related

    /

    DownLoad:  Full-Size Img  PowerPoint
    Return
    Return