Abstract:
Taking the Daya Bay nuclear power plant as a research target, this paper applies the MSHIM strategy on the M310 unit. M310 unit could operate with MSHIM strategy under various modes of operation, including base load and load follow. But the ability of banks of G1, G2, G3 and R is insufficient during load follow. After the redesign of the rod cluster control assembly pattern, the analysis indicates that it is possible to implement the MSHIM strategy on M310 unit with the current placement of control rods.